According to Italian Legislative Decree no. 201/2011, the unfinished works are public works whose construction had been started but had not been completed or even if completed, it is not usable by the community. Unfortunately the national tradition has shown too often the creation of works partially unused and often obsolescent. From March 2013 the Ministry of Infrastructure and Transport started the national census-register of unfinished public works. At the end of 2015, were listed more than 800 works, needing about 1.5 billion euro for completion. To facilitate their completion, the legislator has decided to include them in the contraction authorities three-year programme [...] for the purpose of their completion or for the identification of alternative solutions such as reuse, even resized, supply as remuneration for the construction of another public work, the sale or the demolition. We are confident their completion actually seems very difficult and a new standardization is not enough to ensure good outcome. We investigated possible solutions to reuse the constructed (or partial constructed) public works, some findings about the procedures to their completion, the possible downsizing, the need to consider the technical and management aspects if itВ’s needed a change of use of the work. In case of Piedmont public works, we also estimate the more likely asset value, assuming that works may are unfinished from time but the contracting authorities could use them as remuneration or the estimated demolition costs. What of the public-private partnership? What about low cost intervention to partial complete the works? TheyВ’re both issues that we have to deal with the regional situation, but in general, they may be extended to the national situation.

Publication Impact Profile

Publication details

Title
COMPLETING UNFINISHED WORKS IN ITALY: PROCEDURES, FINDINGS, SYNERGIES
Authors
F.Prizzon, M. Rebaudengo
Proceedings
4th International Multidisciplinary Scientific Conference on Social Sciences and Arts SGEM 2017
Publisher
STEF92 Technology
Year
2017
Pages
115-122
SWS Citekey
Prizzon20173115122
ISSN
2367-5659
ISBN
978-619-7408-15-7
Language
en
Publication type
Proceedings Paper
Keywords
ReferencesPending
Pendingreferences will be imported from Crossref/SWS source data

Structured references will appear here after the reference import pass. The count is preserved now so the scholarly record is not incomplete.

View or Download full articleAccess options
Full paper accessChoose SWS login, librarian support, or instant article download.

SWS access login

Login as SWS Scientific Committee

Authors and approved SWS contributors will read and export their own linked papers after identity matching by SWS profile, email and SGEM GlobalID.

For librarian assistance: [email protected]

Purchase Instant Access

48-hour online accessComing soon
Online-only accessComing soon
Download the full article in PDF formatEUR 35
  • Article can be downloaded after successful payment.
  • Article may be used according to SWS library access terms.
  • Article cannot be redistributed.
Get full paper

Back to publication list